Key takeaways
- Section 460(e) lets residential construction contracts, and other construction contracts expected to finish within 2 years by a taxpayer that meets the gross receipts test of section 448(c), skip the percentage-of-completion rules.
- For taxable years beginning in 2026, that test is an average of $32,000,000 or less in annual gross receipts over the prior 3 years (Rev. Proc. 2025-32, section 4.30).
- Payments to a subcontractor of $2,000 or more made after December 31, 2025 are reportable on Form 1099-NEC. The earlier threshold was $600.
- Davis-Bacon rules require prevailing wages on federally funded or assisted contracts over $2,000, so payroll has to be tracked by job.
A construction company’s books answer a different question from a shop’s books. The shop asks what it earned this month. The contractor asks what each job earned and what it still has to cost. That one change drives the chart of accounts, the way payroll is coded and the tax method the contracts fall under. This guide covers the four rules that show up most often in a contractor’s books, with their current numbers.
Why do construction books run by job?
Every contract is its own small business. Costs for materials, labor, equipment and subcontractors belong to a specific job, and revenue is billed against that job. If the books only show a monthly total, nobody can say whether a kitchen remodel made money or lost it until the job is closed out.
So the usual structure codes each bill, payroll line and subcontractor payment to a job. Reports then show estimated cost, cost to date and billed to date for every open contract. The bookkeeping work is steady and repetitive, which is why a missed job code in March turns into a puzzle in September.
Which contracts skip percentage-of-completion?
Section 460 of the Internal Revenue Code sets the percentage-of-completion rules for long-term contracts. Subsection (e)(1) takes two groups of construction contracts out of those rules (retrieved October 12, 2026).
The first group is any residential construction contract. The second is any other construction contract entered into by a taxpayer who meets two conditions. The taxpayer estimates, when the contract is entered into, that it will be completed within a 2-year period. And the taxpayer meets the gross receipts test of section 448(c) for the year the contract is entered into.
For taxable years beginning in 2026, a corporation or partnership meets that test when the average annual gross receipts for the 3 taxable years before the current one do not exceed $32,000,000 (Rev. Proc. 2025-32, section 4.30). The IRS adjusts the figure each year, so check the number for the year in question.
When does a subcontractor payment need a 1099-NEC?
The IRS says a business reports payments of $600, or $2,000 for payments made after December 31, 2025, during the calendar year for services to a person who is not an employee. The threshold is a calendar-year total per payee, so the books need payments by subcontractor, not only by job.
Pull the totals before the year ends. A subcontractor paid $900 in a year crossed the old $600 line. The same payments in 2026 stay under $2,000 and don’t trigger a form, which is worth knowing when last year’s habits get reused.
What do prevailing wage rules mean for the books?
The Department of Labor says the Davis-Bacon and Related Acts apply to contractors and subcontractors on federally funded or assisted construction contracts in excess of $2,000. They must pay laborers and mechanics no less than the locally prevailing wages and fringe benefits.
For the books, that means payroll has to be coded to the job, with hours by employee and job. A project that falls under these rules needs that record. A project that doesn’t still benefits from it, because labor is the cost most contractors misjudge.
How long should payroll records be kept?
The IRS says to keep employment tax records for at least 4 years after the date the tax becomes due or is paid, whichever is later. For a contractor with seasonal crews and a mix of employees and subcontractors, the sorting at the start of each job is what makes that retention period easy to meet.
Frequently asked questions
Do small contractors have to use percentage-of-completion?
Not for contracts that meet the exception in section 460(e). Residential construction contracts qualify, and so do other construction contracts the taxpayer expects to finish within 2 years if the taxpayer meets the section 448(c) gross receipts test.
What is the 2026 gross receipts limit?
For taxable years beginning in 2026, the test is met when average annual gross receipts for the 3 preceding taxable years do not exceed $32,000,000 (Rev. Proc. 2025-32, section 4.30).
When do I need to send a subcontractor a 1099-NEC?
The IRS says to report payments totaling $600, or $2,000 for payments made after December 31, 2025, during the calendar year for services to a person who is not an employee.
How long should payroll records be kept?
The IRS says to keep employment tax records for at least 4 years after the date the tax becomes due or is paid, whichever is later.
Sources
- Cornell Legal Information Institute, 26 U.S.C., 26 U.S.C. 460, Special rules for long-term contracts, retrieved October 12, 2026.
- Internal Revenue Service, Rev. Proc. 2025-32, 2026 inflation adjustments, section 4.30, retrieved October 12, 2026.
- Internal Revenue Service, Form 1099-NEC and independent contractors, retrieved October 12, 2026.
- US Department of Labor, Wage and Hour Division, Davis-Bacon and Related Acts, construction, retrieved October 12, 2026.
- Internal Revenue Service, How long should I keep records?, retrieved October 12, 2026.
This article is general information about US tax-return rules. It is not tax or legal advice, and your firm should confirm how the rules apply to its own engagements.